Soft strip done
Well its pouring with rain - but most of the internal stuff is now down. 3 weeks of wall demolition coming up ! Slow process as all bricks and floorboards will be recycled. Everybody seems happy . Fabulous job so far by Frank Worbey Demolition.
Demolition is underway
Demolition started this week. All good so far. 'Soft strip' is underway - which is all the stuff inside the current building. 'Hard strip' starts in 1 weeks time. Discussions with a project manager are ongoing and lots of liaison with the council to get the all clear to starting on the foundations in January - with a bit of luck..